Legal provisions of COM(2022)598 - Extension of the joint-undertaking status of Hochtemperatur-Kernkraftwerk GmbH

Please note

This page contains a limited version of this dossier in the EU Monitor.



Article 1

1. The joint-undertaking status, within the meaning of the Treaty, granted to Hochtemperatur-Kernkraftwerk GmbH (‘HKG’) is hereby extended for 5 years with effect from 1 January 2018.

2. The objective of HKG shall be to implement a programme for decommissioning the nuclear power station located at Uentrop (Unna district) in the Federal Republic of Germany, up to the safe enclosure stage and, thereafter, to carry out a programme of surveillance of the enclosed nuclear installations.

Article 2

This Decision shall take effect on the date of its notification.

Article 3

This Decision is addressed to HKG.